Monday, September 29, 2008

Reports done

The Geotechnical and Hydraulic reports have been done, and have been assessed by the engineer along with the results of the sewer peg out. The house is "slightly in the zone of influence" so we will need some additional piering.

We're getting closer to getting the construction certifice, which then means the build can commence! Hopefully should have an update from Wisdom today.

Once again Wisdom have been great - getting the reports done in 2 weeks, whereas they had pregicted 3 weeks.

Wednesday, September 10, 2008

Peg Out Done


Peg out was done on Monday, and the sewer peg out should have been done today.